TECHNICAL GUIDE · ISO 22400

OEE according to ISO 22400: how to calculate it correctly.

Availability, effectiveness and quality ratio explained through the standard: variables, time model, formulae, injection-moulding example, common errors and an interactive calculator.

FORMULA PUBLISHED IN ISO 22400-2

OEE = A × E × Q

A · Availability
E · Effectiveness
Q · Quality ratio

Standards status verified: 2 October 2026.

IN BRIEF

What is OEE under ISO 22400?

OEE (Overall Equipment Effectiveness) is a manufacturing-operations KPI that combines the availability of a work unit, its effectiveness against planned run time per item, and the quality ratio of its output. In the published edition of ISO 22400-2:2014, this KPI is calculated by multiplying these three components.

Variable abbreviations remain in English, as used in ISO 22400: PBT (Planned Busy Time; planned busy time), APT (Actual Production Time; actual production time), PRI (Planned Run Time per Item; planned run time per item), PQ (Produced Quantity; produced quantity) and GQ (Good Quantity; good quantity). The variable abbreviations follow the standard throughout this guide.

Availability = APT / PBT
Effectiveness = (PRI × PQ) / APT
Quality ratio = GQ / PQ
OEE = Availability × Effectiveness × Quality ratio

In this guide, we use effectiveness in the sense used by ISO for Effectiveness, which is the term used in ISO 22400-2. We do not silently substitute the TPM term “performance”: industrial calculators sometimes mix terminology from TPM, MES systems and suppliers, causing indicators based on different definitions to be compared.

Formulae · ISO variables · Downtime classification · Causes and responsibilities · Example · Calculator · Injection moulding · FAQ · References

VERIFIED STANDARDS BASIS

Which edition we use and why.

ISO 22400-1:2014

Defines the framework, concepts and terminology for Manufacturing Operations Management KPIs. ISO states that this edition was reviewed and confirmed in 2025 and remains current.

View the official ISO record →

ISO 22400-2:2014

This is the published edition defining OEE and the formulae for availability, effectiveness and quality ratio. A 2017 amendment addresses energy-related KPIs.

View the official ISO record →

ISO/DIS 22400-2

The second edition remains under development. As of October 2026, ISO lists it at stage 40.99, approved to progress towards FDIS. This guide does not present a draft as a published standard.

View project status →

For practical data acquisition, we also refer to ISO/TR 22400-10:2018, a published technical report on applying ISO 22400-2 formulae to production control and monitoring.

ISO 22400-2 FORMULAE

OEE is the product of three ratios, not their arithmetic mean.

A · AVAILABILITY

A = APT / PBT

Compares actual production time with the time the work unit was scheduled to be busy producing.

E · EFFECTIVENESS

E = (PRI × PQ) / APT

Compares the planned time required for the produced quantity with the actual production time.

Q · QUALITY RATIO

Q = GQ / PQ

Relates the quantity meeting quality requirements to the total quantity produced within the same scope.

OEE = (APT/PBT) × (PRI×PQ/APT) × (GQ/PQ)

ISO 22400-2 specifies a range of 0% to 100% for these indicators. If an implementation produces more than 100%, review planned run time per item, units, quantities and the calculation time boundary rather than interpreting the result as exceptional performance.

TIME MODEL

Five variables suffice to calculate OEE; defining them correctly is the difficult part.

UNDERSTANDING TIME
POT · Planned Operation Time
PBT · planned busy time
planned downtime
Within PBT
APT · actual production
time within PBT without production

This is a conceptual diagram. ISO 22400 defines additional time elements for setup, delays, downtime and other conditions.

VariableDefinitionTypical unit
PBT
Planned Busy Time
Planned busy time, derived from planned operation time minus planned downtime.min, h
APT
Actual Production Time
Actual production time: the period during which the work unit is producing and performing value-adding functions.min, h
PRI
Planned Run Time per Item
Planned run time per item. It must use the same units as PQ and GQ.s/item, min/item
PQ
Produced Quantity
Quantity produced by the work unit within the assessment scope and period.parts, kg, L…
GQ
Good Quantity
Good quantity: output meeting the quality requirements defined for the scope.same unit as PQ

PBT is not simply the length of a shift.

ISO 22400 defines POT (Planned Operation Time; planned operation time) as the scheduled time during which a work unit can be used. Planned downtime is subtracted to obtain PBT. The standard also defines PUST (Planned Unit Setup Time; planned unit setup time) and AUST (Actual Unit Setup Time; actual unit setup time) as separate time elements. A scheduled mould or product change must therefore not automatically disappear from OEE: if it takes place within PBT without value-adding production, it is not part of APT and reduces availability under the published model. The boundary must be established beforehand and kept consistent; changing it after observing losses makes the indicator incomparable.

A useful algebraic cross-check.

For a single product with one PRI value, the APT and PQ terms cancel when the three factors are multiplied:

OEE = (PRI × GQ) / PBT

Use this as a cross-check, not as a substitute for analysing A × E × Q. The reduced expression indicates the equivalent ideal production time for good output within PBT, but hides whether losses came from stoppages, speed or quality. For products with different PRI values, segment by order or product or aggregate ideal times consistently; never substitute an arbitrary common cycle time.

CLASSIFY BEFORE CALCULATING

Downtime is classified by its position in the time model, not by its label.

Two events both called “downtime” in the plant may be treated differently, while events with different causes may affect the same OEE component. The key is to distinguish the mathematical effect from the operating cause.

Cases often interpreted differently.

SituationTreatment under the published ISO 22400 modelWhere it appears in OEEArea of investigation
No shift or production order scheduledIf the period was never included in PBT, it is outside the OEE denominator.Does not reduce OEE, but may matter for utilisation and capacity.Planning, demand and operations management.
Planned preventive maintenanceMay be included in planned downtime subtracted before obtaining PBT.Does not reduce OEE if excluded from PBT at the planning stage.Maintenance and planning.
Maintenance extending into PBTThe portion within PBT is no longer actual production time.Availability.Maintenance; review duration, resources and spare parts.
Mould change, product change or setup adjustmentISO defines AUST (Actual Unit Setup Time; actual unit setup time) separately from APT. If it occurs within PBT, it reduces APT.Availability.Production, tooling and process engineering; SMED where applicable.
Machine failure and corrective maintenanceTime without production within PBT reduces APT. ISO also defines CMT (Corrective Maintenance Time; corrective maintenance time).Availability.Maintenance; then MTBF/MTTR, failure modes and root cause.
Material or component shortageWhen a machine scheduled to produce within PBT waits for supplies, the interval is not APT.Availability.Logistics, planning, procurement or production; do not automatically assign it to maintenance.
Operator absence or missed shift reliefIf production was scheduled but does not occur, APT is reduced. If the absence was excluded from PBT beforehand, it does not enter OEE.Availability or outside OEE, depending on prior planning.Production and personnel management.
Waiting for quality approvalIf a unit scheduled to produce within PBT is stopped, APT decreases.Availability.Quality and production; review release procedure and response time.
Downstream blocking or upstream starvationThe unit is available but not producing. This is consistent with the definition of ADOT (Actual Unit Down Time; actual unit down time despite the unit being available).Availability.Line balancing, internal logistics and production.
Loss of electricity, air, process water or coolingIf production is interrupted during PBT, APT decreases.Availability.Utilities, maintenance and infrastructure.
Micro-stoppages or short interruptionsISO defines ADET (Actual Unit Delay Time; actual unit delay time) for interruptions due to malfunction, minor stoppages and other unplanned intervals. Under the published APT/PBT formulation, non-producing time within PBT reduces availability.Availability under this ISO model; traditional TPM usually assigns minor stops to performance losses.Production and maintenance; document the convention and do not mix models.
Machine producing more slowly than PRIAPT continues; the output takes more actual time than the planned run time per item.Effectiveness.Process engineering, production, maintenance, material or tooling, depending on the cause.
Deliberate speed reductionAn intentional speed reduction does not remove the difference from the applicable PRI. If the new rate is technically appropriate and stable, the master value should be reviewed and versioned, never changed retrospectively.Effectiveness while the approved PRI remains unchanged.Process engineering, quality and tooling.
Scrap, rejected or out-of-specification productReduces GQ relative to PQ.Quality ratio.Quality, process, production, material, mould or machine, depending on the defect mode.
ReworkRules for counting PQ, GQ and RQ must be defined carefully. Rework may change good quantity and, if performed on the same work unit during PBT, may introduce additional time losses.Quality and potentially availability/effectiveness due to additional time.Quality and process engineering; avoid double counting.
Start-up following setupSeparate setup time, slow production and nonconforming start-up parts.May affect availability, effectiveness and quality at different stages.Production, process engineering, quality and tooling.

Micro-stoppages: where measurement conventions are most easily mixed.

Traditional TPM literature groups minor stoppages with speed losses, whereas ISO 22400 defines ADET and, under the published APT/PBT expression, a non-value-adding interruption reduces APT. Research has documented the imperfect correspondence between ISO-defined OEE and historical TPM OEE. Plants should state their calculation model, define consistent rules for short events and retain original cause data to enable recalculation without losing traceability.

Practical guide: measuring and analysing micro-stoppages →

FROM PERFORMANCE INDICATOR TO IMPROVEMENT

OEE aggregates losses; improvement work requires separating them again.

Multiplying A × E × Q summarizes the outcome but does not identify its underlying causes. This aggregation helps quantify the problem but is insufficient for diagnosis. Two production facilities may have the same OEE yet require entirely different interventions.

CASE A · AVAILABILITY IS THE MAIN LOSS
OEE 75.64 %
A 80 %E 99 %Q 95.5 %

Priority may lie in breakdowns, changeovers, waiting or material supply.

CASE B · EFFECTIVENESS IS THE MAIN LOSS
OEE 75.64 %
A 99 %E 80 %Q 95.5 %

Priority may lie in cycle time, process constraints, machine behaviour or tooling.

ISO 22400 does not assign responsibility to departments. The following matrix is a management practice, not a normative requirement. Responsibility should follow the confirmed cause, not the OEE component’s name.

ComponentWhat to break downDepartments that may be involved
AvailabilityFailures, setup, waiting for material, operators, quality release, blocking, utilities, cleaning and maintenance.Production, maintenance, planning, logistics, quality, tooling and utilities.
EffectivenessSlow cycles, reduced speed, operating sequence, cooling, dosing and auxiliary or process constraints.Production, process engineering, maintenance, tooling, materials and automation.
Quality ratioDefect type, cavity, material/batch, process conditions, start-up, inspection and rework.Quality, process engineering, production, tooling, materials and maintenance according to the cause.

The cause must remain identifiable after calculation.

A useful data architecture does not merely store “15 minutes of availability loss”. It records seven minutes of mould change, five minutes waiting for material and three minutes caused by a hydraulic-system alarm, along with product reference, mould, shift, machine and timestamps. This detail allows cause Pareto analysis, assignment of actions and subsequent verification of targeted loss reduction.

How KERN IoP structures the problem.

1. Physical state: cycle, run, alarm signals and available variables. 2. Time-state classification: production, setup, waiting or delay according to documented rules. 3. Cause: automatic code or operator record when the machine cannot identify the reason. 4. Context: order, product, mould, material, shift and auxiliaries. 5. Result: quantity, quality and part measurements. 6. Action: Pareto, responsible teams, follow-up and later comparison.

SMARTHUB brings together signals and the operating records entered on SMARTPRO. MONITOR organises histories, causes and indicators, allowing OEE to be traced back to its underlying events.

Industry 4.0 with people at its centre. OEE becomes useful when plant personnel can interpret losses and decide which problems to investigate. Read more in our guide what Industry 4.0 means and how it supports decision-making in production.

WORKED EXAMPLE · INJECTION MOULDING

480-minute shift, two-cavity mould.

PBT
480 min

APT
420 min

Planned cycle
30 s / 2 cavities

PQ / GQ
1,600 / 1,520 parts

1. Convert the cycle to PRI.

With two active cavities, each planned 30-second cycle produces two units. Therefore: PRI = 30 s / 2 = 15 s/part = 0.25 min/part.

2. Calculate the three factors.

Availability
420 / 480
87.50 %

Effectiveness
(0.25 × 1,600) / 420
95.24 %

Quality ratio
1,520 / 1,600
95.00 %

3. Multiply.

OEE = 0.875 × 0.9524 × 0.95 = 79.17 %

LOSS CASCADE · EQUIVALENT IDEAL TIME
PBT480 min · 100 %
After availabilityAPT = 420 min · 87.50 %
After effectivenessPRI × PQ = 400 min · 83.33 % of PBT
Good-output equivalentPRI × GQ = 380 min · OEE 79.17 %

Quality loss expressed in minutes is an ideal-time equivalent (PRI × rejected parts); it does not mean the machine was stopped for that duration.

INTERACTIVE CALCULATOR

Calculate OEE and explore which factors to improve.

The calculation follows the published ISO 22400-2 formulae for one product over a defined period. The sliders do not promise improvement; they illustrate the mathematical effect of increasing one or more components.

AVAILABILITY—
EFFECTIVENESS—
QUALITY RATIO—
OEE—
Cross-check for a single PRI: OEE = PRI × GQ / PBT = —.

Simulate improvements

Add percentage points to each factor. The simulator caps every factor at 100%.

0 pp
0 pp
0 pp
Simulated OEE—change: —
+1 pp in A
current impact on OEE: —
+1 pp in E
current impact on OEE: —
+1 pp in Q
current impact on OEE: —

DECISIONS THAT AFFECT THE RESULT

A calculation can be correct yet still be incomparable.

Multi-cavity moulds

PRI must use the same unit as PQ. If a planned 30-second cycle produces two parts with two active cavities, PRI is 15 seconds per part. If one cavity is blocked, the units-per-cycle reference must be revised rather than retaining the former divisor.

Different products

Do not average ideal cycle times of different products arbitrarily. Calculate OEE by order or product, or where appropriate aggregate each product’s ideal time as Σ(PRIᵢ × PQᵢ) when calculating effectiveness.

Machine states

Document the classification of setup, waiting, failures, micro-stoppages and slow production. Academic literature identifies differences between ISO-defined and traditional TPM OEE. Meaningful comparison requires consistent state definitions.

Quality ratio is not the same as First Pass Yield.

ISO 22400-2 defines the quality ratio as GQ/PQ. ISO/TR 22400-10 also distinguishes First Pass Yield (FPY), which is associated with the first quality assessment. Successful rework can improve the quality ratio without changing the original first-pass yield. For this reason, the guide does not use “first-time good parts” as an automatic synonym for GQ.

BENCHMARKING

ISO 22400 does not establish a universal 85% OEE target.

The standard defines the KPI, formula, scope, range and behaviour; it does not prescribe a universal 85% target. ISO also notes that thresholds are usually company-specific and that process comparability must be established before benchmarking.

  • Compare equipment and periods using identical definitions of PBT, APT, PRI, PQ and GQ.
  • Do not compare products with substantially different planned run times per item without consistent segmentation or weighting.
  • Use overall OEE to prioritise attention; use A, E and Q to locate the loss category.
  • For continuous improvement, trends measured under stable rules are often more useful than pursuing an external target without context.

FROM KPI TO PLANT-FLOOR DATA

Reliable OEE requires traceability of each variable and loss.

The formula is straightforward. The difficulty lies in preserving the chain linking measurements, states, causes and context. OEE without traceability may reveal that losses exist; a well-structured monitoring system should allow users to trace each loss to its underlying events.

PBT · planning

Calendar, shifts and planned downtime: when the unit was scheduled to produce and which intervals were excluded beforehand.

APT · states and causes

Cycle and state signals help identify production periods. Other intervals must retain their causes: setup, failure, waiting, blocking, material, operator or another reason.

PRI · technical reference

Master data by product, mould, process settings and cavity configuration. Valid changes must be versioned, not used to retrospectively rewrite performance.

PQ and GQ · output

Production and quality counts from machines, personnel or measurement and inspection equipment, synchronised to the same period and context.

How KERN IoP approaches this.

KERN IoP | SMARTHUB collects machine and sensor data along with records that operators enter on SMARTPRO. It can also integrate measurements from scales, machine-vision systems or other instruments when the project interfaces support them. KERN IoP | MONITOR organises variables, historical data and indicators to review performance in the corresponding production context.

The configuration is agreed with the plant and documented: what counts as PBT, how APT is detected, which PRI applies to each product, how micro-stoppages are recorded and which cause codes are used. The goal is not to raise OEE by changing rules, but to maintain a stable basis for verifying that improvements address their intended losses.

OEE · FREQUENTLY ASKED QUESTIONS

Precise answers to common questions.

What is the OEE formula under ISO 22400?

OEE = Availability × Effectiveness × Quality ratio. In ISO 22400-2:2014: A = APT/PBT; E = (PRI×PQ)/APT; Q = GQ/PQ.

Is OEE the average of availability, effectiveness and quality ratio?

No. The three factors are multiplied. Averaging them produces a different indicator.

Should a mould change be excluded because it was scheduled?

Not automatically. ISO distinguishes planned downtime from planned setup. If setup occurs during PBT, it is not included in APT and affects availability in the published OEE model.

Is quality ratio equivalent to First Pass Yield?

Not necessarily. ISO/TR 22400-10 treats FPY as an indicator of the first quality assessment; subsequent rework can improve the quality ratio without changing the initial FPY.

Can OEE exceed 100%?

The ISO specification sets a range of 0% to 100%. A higher result calls for checking PRI, units, quantities and time definitions; it should not be presented as exceptional performance.

Is there a universal 85% “world-class” OEE benchmark?

ISO 22400 does not prescribe such a target. Thresholds must fit the application, and benchmarking requires comparable processes and consistent definitions.

How is PRI calculated for a multi-cavity mould?

If PQ is expressed in parts and one planned cycle produces several parts, PRI must also be per part. At 30 s/cycle with two active cavities, PRI = 15 s/part.

Can products with different cycle times be included in one OEE?

Yes, but not using an arbitrary single ideal cycle. Segmenting by order or product is preferable. If products are aggregated, ideal times must be weighted by the corresponding quantities with consistent units.

How are micro-stoppages classified?

Under the published ISO 22400 formulation, an interruption without value-adding production within PBT reduces APT and therefore availability. ISO defines ADET for minor stoppages and interruptions. Traditional TPM often assigns micro-stoppages to performance losses. The model must be stated and conventions must not be mixed within one time series.

Is a material shortage a maintenance loss?

No. A material shortage during PBT may reduce availability mathematically, but the underlying cause lies in supply, logistics, planning or production. OEE identifies the loss category; the cause code indicates who should investigate it.

Should every planned stoppage be excluded from OEE?

No. Only periods defined in advance as planned downtime are subtracted when determining PBT. ISO defines setup separately; a scheduled changeover can still reduce availability if it occurs within PBT.

Why record causes if every loss ultimately affects OEE?

Because aggregate OEE does not tell teams which action to take. Two machines may have the same OEE but require very different solutions. Retaining causes, durations, context and responsibilities enables Pareto analysis, action assignment and verification.

References

International Organisation for Standardization. (2014). ISO 22400-1:2014. Automation systems and integration — Key performance indicators (KPIs) for manufacturing operations management — Part 1: Overview, concepts and terminology. ISO.

International Organisation for Standardization. (2014). ISO 22400-2:2014. Automation systems and integration — Key performance indicators (KPIs) for manufacturing operations management — Part 2: Definitions and descriptions. ISO.

International Organisation for Standardization. (2017). ISO 22400-2:2014/Amd 1:2017 — Amendment 1: Key performance indicators for energy management. ISO.

International Organisation for Standardization. (2018). ISO/TR 22400-10:2018. Operational sequence description of data acquisition. ISO.

International Organisation for Standardization. (under development). ISO/DIS 22400-2, second edition. Official project status. Accessed 2 October 2026.

Schiraldi, M. M., & Varisco, M. (2020). Overall Equipment Effectiveness: consistency of ISO standard with literature. Computers & Industrial Engineering, 145, 106518. https://doi.org/10.1016/j.cie.2020.106518

Ramis Ferrer, B., Muhammad, U., Mohammed, W. M., & Martínez Lastra, J. L. (2018). Implementing and Visualizing ISO 22400 Key Performance Indicators for Monitoring Discrete Manufacturing Systems. Machines, 6(3), 39. https://doi.org/10.3390/machines6030039

Bokrantz, J., Skoogh, A., Ylipää, T., & Stahre, J. (2016). Handling of production disturbances in the manufacturing industry. Journal of Manufacturing Technology Management, 27(8), 1054–1075. https://doi.org/10.1108/JMTM-02-2016-0023

Hung, Y.-H., Li, L. Y. O., & Cheng, T. C. E. (2022). Uncovering hidden capacity in overall equipment effectiveness management. International Journal of Production Economics, 248, 108494. https://doi.org/10.1016/j.ijpe.2022.108494

TECHNICAL REVIEW

Dr.-Ing. Miguel Garzón · Technical Director, KERN IoP

Reviewed by the technical management of KERN IoP, a division of PM Tec Engineering. Last reviewed: October 2026. Technical profile and publications →


PM Tec Engineering, through its Industry 4.0 division, KERN IoP.
Cota, Cundinamarca · Colombia.
© 2026 PM Tec Servicios de Ingeniería SAS · Website updated in 2026.

Privacy policy